Construction Project Update

Shared Streets Projects - Phase 2 pilots

Austin · Austin Project Explorer

This city’s feed has changed within the last week. We check every morning.

StatusConstruction
Stageactive
StartDec 2022
CompletionDec 2027
Budget$693,970
CityAustin
SourceAustin Project Explorer
Source IDaustin_project_explorer:13269.004
CategoryMobility Infrastructure
District(s)1,3
Finish (raw)Anticipated Winter 2027-28
Spent to date ($)$2,682,741
Start (raw)Winter 2022-23

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-11-02Routinebudget cut 76% ($2,939,685 -> $693,970)