Center Street Pump Station Replacement and Electrical Improvements

Austin · Austin Project Explorer

This city’s feed has changed within the last week. We check every morning.

StatusActive
Stagedesign
StartJun 2029
CompletionSep 2032
Budget$67,002,136
CityAustin
SourceAustin Project Explorer
Source IDaustin_project_explorer:2006.059
CategoryWater
District(s)3
Finish (raw)Anticipated Fall 2032
Spent to date ($)$11,732,408
Start (raw)Anticipated Summer 2029
Sub-categoryWater

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-11-02Routinecompletion date slipped ~1.0 years
2026-10-27Routinestart date slipped ~6 months